Quote to Cash - Project Details / Task List

Tag: quote-to-cash Total Hours: 175h Structure: Multi-Milestone (>50h)


Milestone 1: Quote to Cash - 1. Discovery & Configuration

Tag: quote-to-cash Description: Discovery, vendor selection, CPQ configuration, and CLM integration setup Hours: 75h

Task List: (Quote to Cash) 1. Discovery & Vendor Selection

Contains: Parts 1-2

TaskEstDescription
1. Map the Existing Q2C Process Flow4hDocument the complete current-state workflow from quote creation through cash collection, identifying all systems, handoff points, and manual processes. End state: Visual process map showing each stage, system touchpoints, and data flow gaps.

• Interview stakeholders from Sales, Finance, Legal, and Operations to understand their role in Q2C
• Document current tools used at each stage (CRM, spreadsheets, CPQ if any, contract tools, billing system, ERP)
• Map data flow between systems and identify manual re-entry points
• Identify the "dark zones" where data doesn't transfer automatically (e.g., quote to contract, contract to invoice)
• Calculate current quote-to-cash cycle time and benchmark against industry standards (84 days average for B2B SaaS)
2. Quantify Revenue Leakage and Inefficiencies4hMeasure the financial impact of current Q2C gaps including billing errors, payment delays, and manual effort costs. End state: Business case document with quantified losses and improvement targets.

• Pull billing error rate data from finance (incorrect invoices, credit memos, disputes)
• Calculate involuntary churn from payment failures (industry average is 0.8% of MRR)
• Measure time spent on manual quote creation, approval chasing, and invoice generation
• Identify revenue recognition issues or audit findings from past periods
• Document compliance gaps (ASC 606/IFRS 15 manual workarounds)
• Quantify the gap (e.g., "15% of invoices require manual correction, costing 20 hours/week")
3. Define Requirements and Success Metrics3.5hGather requirements from all stakeholder groups and establish measurable success criteria. End state: Requirements document with prioritized features and KPIs.

• Conduct requirements workshops with Sales (quoting needs), Finance (billing/rev rec needs), Legal (contract needs)
• Document must-have vs. nice-to-have capabilities
• Define approval workflow requirements (discount thresholds, deal desk involvement)
• Establish success metrics: cycle time reduction target, error rate target, automation percentage
• Get executive sign-off on requirements and success criteria
4. Build Evaluation Criteria and Shortlist3.5hCreate structured evaluation framework and identify candidate Q2C platforms based on requirements. End state: Shortlist of 3-4 vendors with evaluation scorecard criteria.

• Define evaluation criteria: CPQ capabilities, CLM features, billing automation, revenue recognition, integration depth
• Weight criteria based on client priorities (e.g., compliance vs. speed vs. cost)
• Research candidate platforms (DealHub, Subskribe, Maxio, Salesforce Revenue Cloud, Nue.io, Conga)
• Note: Salesforce legacy CPQ entering End of Sale March 2025; consider Revenue Cloud for SF shops
• Create shortlist of 3-4 vendors that match tech stack (CRM, ERP compatibility)
5. Conduct Vendor Demos and POC6hRun structured vendor demonstrations and proof-of-concept tests on core workflows. End state: Completed vendor scorecards with demo notes and POC results.

• Schedule vendor demos with standardized agenda covering all key use cases
• Prepare demo scenarios: standard quote, complex deal with discounts, contract amendment, invoice generation
• Evaluate ease of use for sales reps (adoption is critical)
• Test integration approach with existing CRM (Salesforce/HubSpot) and ERP (NetSuite/SAP)
• Score each vendor against evaluation criteria
• Conduct POC with top 1-2 vendors on actual client data if possible
6. Finalize Selection and Procurement3hMake final vendor recommendation, negotiate contracts, and complete procurement. End state: Signed vendor agreement with implementation timeline.

• Present recommendation to stakeholders with pros/cons analysis
• Negotiate licensing terms (per-user vs. transaction-based, annual vs. multi-year)
• Clarify implementation support included vs. additional cost
• Review data security and compliance certifications (SOC 2, GDPR)
• Finalize contract and initiate procurement process
• Establish implementation kickoff date

Task List: (Quote to Cash) 2. CPQ & CLM Configuration

Contains: Parts 3-4

TaskEstDescription
7. Configure Product Catalog and Pricing Rules8hSet up the product catalog, pricing structures, and discount rules in the CPQ system. End state: Complete product catalog with pricing logic that mirrors current rate card and business rules.

• Import or build product catalog with all SKUs, bundles, and service offerings
• Configure pricing tiers (volume-based, customer segment-based)
• Set up discount approval thresholds (e.g., <10% auto-approve, 10-20% manager, >20% deal desk)
• Build pricing rules for common scenarios (multi-year discounts, payment term adjustments)
• Ensure SKU naming conventions match billing system to prevent reconciliation issues
• Test pricing calculations against known good quotes
8. Build Quote Templates and Document Generation6hCreate quote document templates and configure automated document generation. End state: Professional quote templates that auto-populate with deal data and generate PDFs.

• Design quote template with branding, terms summary, and pricing table
• Configure dynamic fields that pull from CRM opportunity and CPQ configuration
• Set up multiple templates for different scenarios (new business, renewal, expansion)
• Build approval stamp/signature block for internal approvals
• Test document generation with sample data
• Get Sales and Legal sign-off on template format
9. Configure Approval Workflows6hBuild multi-stage approval workflows based on deal characteristics. End state: Automated approval routing that enforces discount policies and deal desk requirements.

• Map current approval matrix (who approves what based on discount, deal size, terms)
• Configure approval workflow stages in CPQ
• Set up notifications and escalation paths for stalled approvals
• Build deal desk queue for complex deals requiring manual review
• Configure mobile/email approval capabilities for managers
• Test approval routing with scenarios at each threshold level
10. Configure Contract Templates and Clause Library8hSet up contract templates and build a clause library for standard and negotiated terms. End state: Master service agreement and order form templates with modular clause options.

• Import or create MSA, Order Form, and Amendment templates
• Build clause library with pre-approved language options (payment terms, liability caps, SLAs)
• Configure fallback clauses for negotiation scenarios
• Set up contract metadata fields (effective date, term length, renewal terms, auto-renewal)
• Integrate Legal playbook guidance for when to escalate non-standard terms
• Test template generation from CPQ quote data
11. Build Contract-to-Quote Data Flow10hEstablish bidirectional data sync between CPQ and CLM so quotes automatically generate contracts and contract changes update deal records. End state: Seamless quote-to-contract flow without manual data re-entry.

• Map CPQ fields to CLM contract fields (products, pricing, customer info)
• Configure automatic contract generation when quote reaches "approved" status
• Build sync for contract status back to CRM opportunity (sent, negotiating, signed)
• Set up version control for contract amendments during negotiation
• Configure signature routing through e-signature tool (DocuSign, PandaDoc, Ironclad)
• Test end-to-end flow: quote approval triggers contract, signature triggers deal close
12. Configure Amendment and Renewal Workflows13hBuild workflows for mid-contract amendments and renewal scenarios. End state: Amendment and renewal processes that keep CPQ, CLM, and billing in sync.

• Configure amendment workflow for add-ons, upgrades, and downgrades
• Build proration logic for mid-term changes
• Set up renewal notification triggers (90/60/30 days before expiration)
• Configure auto-renewal handling vs. manual renewal process
• Establish version tracking so amendments reference original contract
• Test amendment scenario: customer adds seats mid-contract, verify proration calculates correctly

Milestone 2: Quote to Cash - 2. Billing & Revenue Recognition

Tag: quote-to-cash Description: Billing system integration, invoicing, revenue recognition, and compliance setup Hours: 45h

Task List: (Quote to Cash) 3. Billing & Revenue Recognition

Contains: Parts 5-6

TaskEstDescription
13. Map Contract Data to Billing Records8hConfigure the integration between CLM/CPQ and billing system so signed contracts automatically create billing records. End state: Signed contracts trigger invoice schedules without manual billing setup.

• Map contract fields to billing system fields (customer, products, pricing, dates, payment terms)
• Configure billing record creation trigger (contract signed, start date, etc.)
• Set up invoice schedule generation (monthly, quarterly, annual, milestone-based)
• Handle proration logic for mid-period starts
• Build SKU mapping table to resolve any naming differences between CPQ and billing
• Test: signed contract generates correct invoice schedule automatically
14. Configure Invoice Generation and Delivery7hSet up automated invoice generation, formatting, and delivery to customers. End state: Invoices auto-generate and deliver on schedule with correct line items and amounts.

• Configure invoice template with branding and required fields (PO number, billing contact)
• Set up invoice generation schedule (day of month, X days before due date)
• Configure delivery methods (email, customer portal, EDI for enterprise customers)
• Build dunning sequence for overdue invoices (reminder at 7/14/30 days)
• Set up credit memo and refund workflows for billing corrections
• Test invoice generation and verify amounts match contract terms
15. Connect Payment Collection and Cash Application8hIntegrate payment gateways and configure cash application to close the loop from invoice to collected revenue. End state: Payments auto-apply to invoices with minimal manual reconciliation.

• Integrate payment gateway(s) (Stripe, ACH, wire, credit card)
• Configure automatic payment for customers on recurring billing
• Set up payment matching rules for manual payments (check, wire)
• Build failed payment retry logic and dunning escalation
• Configure cash application to match payments to open invoices
• Monitor involuntary churn metrics and payment failure rates
16. Configure Revenue Recognition Rules8hSet up ASC 606/IFRS 15 compliant revenue recognition in the billing or ERP system. End state: Revenue schedules auto-generate based on contract terms and performance obligations.

• Document client's revenue recognition policy (point-in-time vs. over time, performance obligations)
• Configure rev rec rules in billing/ERP system for each product type
• Set up deferred revenue handling for prepaid contracts
• Build revenue schedule generation from contract terms (pro-rata, milestone, usage-based)
• Configure handling for multi-element arrangements (software + services bundles)
• Validate rev rec treatment with Finance/Accounting team
17. Build Audit Trail and Compliance Reporting7hEstablish audit-ready documentation and compliance reporting for revenue transactions. End state: Complete audit trail from quote through recognized revenue with compliance reports.

• Configure audit logging for all quote, contract, invoice, and payment changes
• Build compliance reports for ASC 606 disclosure requirements
• Set up data retention policies for quotes, contracts, and invoices (7+ years typical)
• Document revenue recognition methodology for auditors
• Create reconciliation reports: bookings vs. billings vs. revenue
• Test audit trail by tracing sample deal from quote through rev rec
18. Set Up Financial System Integration7hConfigure integration between billing system and general ledger/ERP for financial close. End state: Billing data flows to GL automatically with proper account mapping.

• Map billing line items to GL account codes (revenue, deferred revenue, AR)
• Configure journal entry generation frequency (daily, weekly, real-time)
• Build reconciliation reports between billing system and GL
• Set up month-end close automation for revenue reports
• Test month-end close process with Finance team
• Document close calendar and integration touchpoints

Milestone 3: Quote to Cash - 3. Testing & Deployment

Tag: quote-to-cash Description: End-to-end testing, user acceptance, training, and phased rollout Hours: 55h

Task List: (Quote to Cash) 4. Testing & Deployment

Contains: Parts 7-8

TaskEstDescription
19. Execute End-to-End Integration Testing8hTest the complete Q2C flow from quote creation through revenue recognition with realistic scenarios. End state: Validated end-to-end workflow with documented test results.

• Create test plan covering all Q2C stages and integration points
• Execute test scenarios: new customer, expansion, renewal, amendment, cancellation
• Test edge cases: complex discounts, multi-currency, international tax, custom terms
• Verify data accuracy at each handoff point (CPQ to CLM, CLM to billing, billing to GL)
• Document integration failures and work with vendors to resolve
• Achieve sign-off on integration testing before UAT
20. Conduct User Acceptance Testing (UAT)8hRun UAT with actual users from Sales, Finance, and Operations to validate usability and accuracy. End state: UAT sign-off from all stakeholder groups.

• Recruit UAT participants from each user group (sales reps, managers, deal desk, finance)
• Create UAT scripts based on their daily workflows
• Facilitate UAT sessions with guided scenarios and open exploration
• Track issues and categorize (blocker, major, minor, enhancement)
• Work through blockers and major issues before go-live
• Obtain formal UAT sign-off from each stakeholder group
21. Perform Data Migration and Validation8hMigrate historical data (products, customers, contracts, pricing) and validate accuracy. End state: Clean, validated data in production systems ready for go-live.

• Define data migration scope (active contracts, pricing history, customer records)
• Extract and transform data from legacy systems
• Load data into Q2C platform(s) with validation checks
• Reconcile migrated data against source systems
• Clean up duplicates and data quality issues
• Get Finance approval on migrated financial data accuracy
22. Develop Training Materials and Documentation6hCreate role-specific training materials, quick reference guides, and process documentation. End state: Complete training curriculum and documentation package.

• Build training deck covering Q2C process overview and system workflows
• Create role-specific guides: Sales (quoting), Deal Desk (approvals), Finance (billing/rev rec)
• Develop quick reference cards for common tasks (create quote, process amendment, generate invoice)
• Document troubleshooting procedures for common issues
• Record video walkthroughs for self-service learning
• Build FAQ based on UAT feedback and questions
23. Conduct Training Sessions6hDeliver training to all user groups with hands-on practice in the system. End state: All users trained and confident using the new Q2C workflow.

• Schedule training sessions by role (Sales team, Deal Desk, Finance, Operations)
• Deliver live training with hands-on exercises in sandbox environment
• Allow time for questions and real-world scenario practice
• Distribute training materials and documentation
• Set up office hours for follow-up questions during first 2 weeks
• Track training completion and follow up with no-shows
24. Execute Phased Rollout10hLaunch Q2C system in phases to minimize disruption and allow for iterative improvements. End state: System live in production with all users active.

• Define rollout phases (by team, region, product line, or deal type)
• Launch Phase 1 with pilot group and monitor closely
• Maintain parallel processing with legacy systems during transition period
• Track adoption metrics (quotes created, approval times, invoice accuracy)
• Address issues discovered in each phase before expanding
• Execute cutover to full production once pilot phase validates stability
25. Establish Ongoing Support and Optimization9hHand off to client team with support structure and continuous improvement plan. End state: Client self-sufficient with documented processes and optimization roadmap.

• Transfer admin credentials and documentation to client RevOps/IT team
• Define escalation path for issues (internal support vs. vendor support)
• Schedule 30/60/90 day check-ins to review performance metrics
• Create optimization backlog based on user feedback and performance data
• Document recommended enhancements for Phase 2 (advanced analytics, additional integrations)
• Close out project with executive stakeholder review

Summary

  • Total Milestones: 3 (75h + 45h + 55h)
  • Total Task Lists: 4 (consolidated from 8 Parts)
  • Total Tasks: 25 (one per Step)
  • Total Hours: 175h
  • Generated from: playbook_quote-to-cash.md
  • Generated on: 2025-12-31